Engineering challenge

Throughout the entire course of phase 2, solutions will have to be developed to deal with the high temperatures on the one hand and the sand, dust and dune movement on the other.

Temperature gradient

The temperature gradient is not much higher in Saudi Arabia than in many southern regions of Spain, where the high-speed railway lines had been built following a similar methodology to the one included in the bid for the Haramain High Speed Railway.

In the summer months, Seville, Jaén, Córdoba, Ronda, Los Monegros and Albacete reach peak temperatures similar to those on the Arabian Peninsula, and sometimes even higher. However, one important consideration made the Saudi project more difficult: the extreme thermal fluctuations, with maximum annual temperatures higher than fifty degrees and minimums close to or even lower than ten degrees, which posed a technical and human challenge.

Infrastructure solutions

Most of the technical studies were aimed at avoiding the potential effects of sand on the infrastructure, the tracks, the systems and the rolling stock. The risks of the platform being invaded with dune advancement were high, in addition to the contamination of the track superstructure and the rolling stock with the sand and dust carried in the wind.

From the start, the entire route was monitored to detect the zones where the most sand accumulated. Furthermore, the possible impact of sandstorms, which reach heights of up to six kilometres, was exhaustively researched.

Construcción de la vía en balasto y en placa

Division of the construction into ballast and slab tracks

Slab tracks were installed slab tracks on the 30 kilometres that were the most exposed to this phenomenon, in addition to implementing complementary solutions as well. The construction of slab tracks is essentially designed to make maintenance and cleaning easier. The maintenance includes special devices to collect sand, when needed.

Other studies performed by CEDEX which analysed the behaviour of the ballast when it is contaminated by desert sand in different degrees of silting demonstrated that the elastic behaviour of ballast tracks silted with sand was higher than that of unsilted ballast tracks.

Installation of one-metre prefabricated concrete retaining walls along eighty kilometres

An empirical study complementary to a theoretical study on the behaviour of sand analysed the accumulation of sand on the platform to determine the best sites to install the walls along the route. By building these prefabricated concrete walls, the sand which was not held back by the fence is kept at bay, as the last physical barrier against it.

Alta velocidad La Meca - Medina muros de contención tramos de vía urbana

Sand traps

On the most conflictive stretches with the highest sand accumulation, ditches were dug, sand traps that were covered with rubble to prevent the dunes from reaching the platform. The client had these sand traps built in the previous phase. This measure is also designed to facilitate track maintenance.

Installation of a sand blowing system

Front blowers were installed on the trains to eliminate the sand deposited on the tracks.

Engineering companies:

Consultrans e INECO

Last HIGHLIGHS of Proyect
Stationary and mobile communications

Stationary and mobile communications

The communication systems are the artery through which information on the railway operation flows in real time. The stationary communication system is carried in a fibre optic wire which runs along two conduits, one on each side of the track, parallel to the railway...

read more
Design, Acquisition and Maintenance of the Rolling Stock

Design, Acquisition and Maintenance of the Rolling Stock

One factor that weighed heavily in the choice of the Al Shoula proposal is the international fame of the Spanish train fleet, its low carbon dioxide emissions and the Spanish manufacturers’ experience with high speed trains, among many other important reasons. The...

read more
Recommended highlights of TRAIN OF THE DESERT
The Construction of the Superstructure

The Construction of the Superstructure

The contract to execute phase 2 of the Haramain High Speed Railway went into effect on 15 September 2012. The division of the platform: Six areas and eight stretches The route of the railway line, 450 kilometres long, was divided into six areas for phase 1. For phase...

read more
Construction of the Infrastructure and Associated Systems

Construction of the Infrastructure and Associated Systems

Immediately after the contract for phase 2 entered into force on 15 September 2012, the different work stages in building the superstructure and systems got underway. In Spain and on the ground in Saudi Arabia, the Spanish companies in the consortium deployed a...

read more